Choose an exhibition stand builder for IFEMA Madrid by relevant delivered work, a clear technical scope, named responsibilities and an itemised proposal for your actual event. Stand costs and deadlines depend on the allocated plot, activities, current event documents, equipment, construction and service requirements.
This checklist helps you compare suppliers and budget assumptions. For booking and document collection, see the IFEMA Madrid exhibitor guide. For a hotel or congress room, use the separate Madrid venue and contractor guide.
Give every builder the same information
Send the event edition, organiser, hall, plot plan, dimensions, open sides and current exhibitor manual. Include products, equipment dimensions and weights, demonstrations, meeting needs, storage, staff numbers, content, budget scope and intended future use.
Separate confirmed inputs from provisional ones. If the plot, equipment or graphics are undecided, ask the supplier to explain assumptions and the cost or timing consequences of a change. A quotation based on a different brief is difficult to compare fairly.
Compare designs by their proposed use
| Proposal | Questions to resolve |
|---|---|
| Organiser package or shell scheme | What structure, graphics, lighting, power, furniture and services are included? What alterations and additional equipment are permitted? |
| Modular construction | Which system and configuration are proposed? What are its documented limits, graphic dimensions, transport and adaptation needs? |
| Custom construction | Which features address the brief? How will drawings, samples, technical review, production and later use be controlled? |
| Mixed construction | Which elements use a system and which are bespoke? Who is responsible for their compatibility and technical review? |
| Rental or purchase | Who owns each item? What are the return, damage, storage, maintenance and reuse terms? |
Rental is an ownership arrangement and can apply to different construction methods. A modular system is not automatically cheaper or quicker for every project. Custom construction does not guarantee greater footfall or commercial results.
Review the plan around actual activities: a demonstration needs operating and viewing space; a meeting needs appropriate furniture and circulation; stock needs accessible storage. Confirm the technical and event acceptability of proposed features before committing to them.
Separate the main budget groups
A useful budget distinguishes participation, the stand, services and the exhibitor’s own operating costs. Ask who contracts and pays each item so that a builder’s price is not mistaken for the complete cost of exhibiting.
- Participation: space, event packages, insurance and other charges in the organiser’s contract.
- Stand: design, technical documentation, construction or rental, graphics, finishes, furniture and equipment.
- Delivery: packing, transport, access, handling, installation, testing and handover.
- Operation: power and other ordered services, connectivity, cleaning, staffing, content and contracted support.
- Return: dismantling, waste handling, return transport, damage, refurbishment and storage.
Identify taxes, provisional amounts, exclusions, overtime and change charges. Ask whether quantities are fixed and how a revised design is priced. Keep the supplier quotation date and validity period with the comparison.
A price per square metre can describe a specific quotation, but it can hide differences in equipment, services and technical scope. Compare total costs for the same deliverables. Avoid applying another fair’s space tariff or a historic stand price to your project.
Build the schedule around real requirements
Use official submission, ordering, access and removal dates. Add the supplier’s proposed decision deadlines, specialist reviews, artwork checks, material availability, production, packing and transport. Ask which tasks depend on earlier decisions and where unresolved questions could affect delivery.
IFEMA’s technical support page directs exhibitors to each fair’s specific exhibitor guide. Check that guide and the applicable general rules rather than assuming a universal approval deadline, height limit or installation window.
Assign responsibility for checking the technical requirements, preparing documents, submitting them, tracking replies and addressing conditions. An internal approval of a render is not permission to build. Confirm any requirements for rigging, structures, electrical work, materials or activities with the responsible specialists and organiser.
Ask for evidence of delivery capability
Request projects relevant to your venue, activities and proposed construction. Record the event, year, actual scope and supplier’s role. A photograph can show a delivered appearance, but it cannot establish hidden technical work, the complete contract or commercial performance.
For visual context, Adam Expo Stand publishes the SGS Dental at Expodental and Alphacan at VETECO projects. Use identifiable examples to ask concrete questions; do not infer your own project’s price or results from them.
Establish the proposed team, production arrangements and specialist partners. Ask who owns quality checks and site issues. A local workshop can be relevant to a particular plan, but location alone does not prove spare capacity, faster repairs or lower cost.
Agree delivery and handover responsibilities
Confirm the receiving contact, access booking, unloading and handling arrangements, installation team, service connections and return plan. Check the current venue vehicle instructions. Do not confuse a delivery booking with an approved stand design or a completed service order.
Agree acceptance checks for the contracted work and how incomplete items will be recorded. Name the site lead and support contact, with availability and escalation arrangements. Keep technical restrictions clear so staff know when an affected feature must remain out of use.
Record the returned inventory, damage and condition after the event. For a repeat programme, compare storage, adaptation, graphics, repairs and transport as well as the original stand price.
Frequently asked questions
How much does an IFEMA stand cost?
Request a dated quotation for the actual plot, activities and deliverables. Add organiser charges, services, exhibitor operations and return costs. There is no single verified design-and-build rate that covers every IFEMA event and stand.
When should I appoint the builder?
Start once the participation scope is known and check the official deadlines promptly. The supplier should confirm a feasible schedule for the proposed design, approvals, production and access arrangements.
Does a turnkey price include everything?
Read the written inclusions, exclusions and responsibilities. Confirm technical submissions, venue orders, transport, support, dismantling and storage individually.
What is the next step?
Send Adam Expo Stand the event manual, plot, activities, equipment, budget and dates. Request a proposed scope, availability, itemised costs and a decision schedule for review.
Follow our exhibition planning guides